    Arizona Asbestos NESHAP Regulations for Demolition and Renovations

    Arizona Asbestos NESHAP Regulations for Demolition and Renovations

    A pdf page outlining the asbestos NESHAP regulations for contractors in Arizona

    Renovations — Facilities undergoing renovations


    must submit a NESHAPs notification if greater than
    threshold amounts of RACM are disturbed.
    Threshold amounts are:
    • 260 linear feet (for materials on pipes)
    • 160 square feet (for surface areas)
    • 35 cubic feet (for materials

    What everyone needs to remember when considering demolition or renovations of a facility is that NESHAP’s applys to All facilities, regardless of the date of construction.

    If the project is in Maricopa County the following applies:

     Thoroughly inspect the facility within 12 months of commencement of demolition or renovation activity. Include the date of this inspection on the written notification. *(All facilities, regardless of the date of construction)

     

    http://www.azdeq.gov/environ/air/asbestos/download/neshap_demo.pdf